There are three different methods of estimation Center line method, Long and short wall method, And Crossing method. In this article, I will discuss center line method briefly for the estimation of materials.
What Is Center Line Method?
In this method of estimation, the total center line length of walls in a building is first calculated, then the center line length is multiplied with the breadth and depth of the respective items to get the total quantity at a time.
The center line length for different sections of walls in a building shall be worked out separately. For verandah walls or partition walls joining the main walls, the center line length shall be reduced by half of the breadth of the layer of the main wall that joins with the partition or verandah wall at the same level. The number of such joints is studied first to obtain the center line length.
By using this method estimation can be finished more quickly. This method is as accurate as other methods (except for unsymmetrical walls). This method is suitably used for estimating circular, rectangular, hexagonal, octagonal, etc. shaped buildings.
Let us take an example:
For One Room Building
First, we need to calculate the total center line length of the building.
Total center line length = 2 x 5.3 + 2 x 4.3 = 19.2 m.
1. Earthwork in excavation = Total center line length x breadth x depth
= 19.2 x 0.9 x (0.3+0.3+0.3)
= 19.2 x 0.9 x 0.9
= 15.52 m3
2. Concrete in foundation = 19.2 x 0.9 x 0.3 = 5.18 m3
3. a) Brickwork in foundation for 1st footing = 19.2 x 0.6 x 0.3 m3
b) Brickwork in foundation for 2nd footing = 19.2 x 0.5 x 0.3 = 2.88 m3
4. Brickwork in superstructure = 19.2 x 3.5 x 0.3 = 20.16 m3
For Two Room Building:
Total center line length = 2 x (5.3+5.3) + 3 x 4.3 = 34.1 m.
1. Earthwork in excavation = Total center line length x breadth x depth
= 34.1 x 0.9 x (0.3+0.3+0.3)
= 34.1 x 0.9 x 0.9
= 27.62 m3
2. Concrete in foundation = 34.1 x 0.9 x 0.3 = 9.20 m3
3. a) Brickwork in foundation for 1st footing = 34.1 x 0.6 x 0.3 = 6.13 m3
b) Brickwork in foundation for 2nd footing = 34.1 x 0.5 x 0.3 = 5.11 m3
4. Brickwork in superstructure = 34.1 x 3.5 x 0.3 = 35.8 m3
Thus you can estimate the quantity of different items such as
Quantity of D.P.C = Total Centre line length x Breadth of foundation x Thickness of D.P.C
Quantity of plinth beam = Total Centre line length x Breadth of the beam x Depth of beam.
Quantity of wall plaster for 2 sides = Total center line length x Height of wall x Thickness of plaster.
Quantity of Paint for 2 sides of wall = Total center line length x Height of wall x 2 = Area of paint in sq.ft
Also Read
For More Updates like our Facebook Page and join our Telegram Channel.
layout of buildind practical file in hindi 5by4
appretus……..?
method………?
result…………?
dising …….?
Very useful for beginners.
nice information
there should be two raw plan its quit nice information but i want to learn more then 5 room plan please provide if you can
What is main principle of center line method..?
The principle is “Centre line” itself …
Very useful information
It is good information
NEED DEDUCTION AT JUNCTION POINT FOR MORE ACCURATE QUINTITY.
2X(0.3/2)X0.3=0.09 AREA X THICKNESS